Mumbai Infra Update: BMC To Begin TBM Work On Kasheli-Mulund Water Tunnel By September; 7.13-Km Project Targeted For 2030 Completion
· Free Press Journal

Mumbai, July 22: Mumbai's ambitious Kasheli (Bhiwandi)-Mulund Octroi Naka water tunnel project is set to enter its most crucial phase, with tunnel boring using a Tunnel Boring Machine (TBM) scheduled to begin by September. The 7.13-km-long, 4.5-metre-diameter tunnel is expected to be completed by October 2030.
The project is part of the BMC's plan to improve the efficiency of the city's water distribution system by reducing transmission losses through a new underground water conveyance network.
Visit playerbros.org for more information.
TBM Work To Begin
Additional Municipal Commissioner (Projects) Abhijit Bangar reviewed the project during a site visit and directed officials to maintain the pace of work while ensuring quality, safety and adherence to timelines. The tunnel has been under construction since September 2024.
पाणी वितरण व्यवस्थेतील गळती कमी करून पाणीपुरवठा अधिक कार्यक्षम व सक्षम करण्याच्या उद्देशाने, बृहन्मुंबई महानगरपालिकेमार्फत कशेळी महासंतुलन जलाशय ते कशेळी (भिवंडी) तसेच कशेळी ते मुलुंड जकात नाका या दरम्यान पाणी वहनासाठी दोन स्वतंत्र जलबोगद्यांच्या बांधकामाची कामे वेगाने… pic.twitter.com/u0Y7ss1Ify
— माझी Mumbai, आपली BMC (@mybmc) July 22, 2026
According to civic officials, all components of the 5.3-metre-diameter TBM, along with the 14-km-long conveyor system required for excavation, have reached the project site. At Kasheli, excavation of the 128-metre-deep recovery shaft, which will be used to retrieve the TBM after tunnelling, has progressed to a depth of 27 metres.
At the Mulund end, the 134-metre-deep launching shaft has been completed, along with excavation of the 95-metre assembly tunnel, the 40-metre tail tunnel and the 25-metre tube tunnel. RCC lining work for the shaft has also commenced.
Bangar said the project will provide an additional underground corridor to carry water from the Bhatsa system, helping reduce transmission losses and improve the reliability of Mumbai's water supply. He directed officials to complete the project as per schedule and maintain the highest standards of construction quality and safety.
मुंबईतील तृतीय संस्करण (Tertiary Treatment) केलेल्या पाण्याचा पुनर्वापर वाढविण्यासाठी बृहन्मुंबई महानगरपालिकेमार्फत दोन महत्त्वाच्या जल बोगद्यांचे बांधकाम सुरू आहे. या प्रकल्पांतर्गत घाटकोपर मलजल प्रक्रिया सुविधा केंद्र ते भांडुप संकुल (पॅकेज-१) आणि धारावी मलजल प्रक्रिया… pic.twitter.com/NKPxtydNpq
— माझी Mumbai, आपली BMC (@mybmc) July 22, 2026
Wastewater Tunnel Progresses
Meanwhile, the BMC's underground tunnel project to transport tertiary-treated wastewater has reached a key milestone, with tunnel boring for the 11.61-km Ghatkopar–Bhandup tunnel scheduled to begin in January 2027.
To expand the reuse of treated wastewater, the BMC is constructing two dedicated conveyance tunnels linking Ghatkopar STP to the Bhandup Complex and Dharavi STP to Ghatkopar STP.
Also Watch:
Mumbai Malad STP Upgrade On Track For July 2028 Completion, To Boost Sewage Treatment CapacityFor the Ghatkopar–Bhandup stretch, excavation of the 175-metre-deep Bhandup shaft has reached 136 metres, while work has progressed to 8 metres and 25 metres at the two shafts within the Bhandup STP.
Once completed, the tunnel will carry tertiary-treated water for industrial and other non-potable uses, reducing dependence on potable water and strengthening Mumbai's water sustainability.